Enlarged norms of time for maintenance, repair and metrological support of instrumentation and automation. Maintenance of instruments of instrumentation Norms of time for maintenance of instruments

In this article you can get acquainted with: operations carried out during the maintenance of the bridge (potentiometer); norms of time for performing operations; bridge (potentiometer) maintenance strategy. Operations Discharge Execution time (hour) Maintenance strategy Replacing the chart tape. 4 0.08 TO1 Cleaning the print carriage, soaking the felt with ink 4 0.06 TO1 External inspection in accordance with the requirements for explosion-proof equipment.…

Category: Tags: ,

In this article you can familiarize yourself with: the operations carried out during the maintenance of a panel milliammeter; norms of time for performing operations; maintenance strategy for the switchboard milliammeter. Operations Discharge Execution time (hour) Maintenance strategy External inspection in accordance with the requirements for explosion-proof equipment, removal of contamination. 5 0.06 TO3 Checking zero 5 0.04 TO3 Checking the reliability of fastening of all nodes, ...

Category: Tags: ,

In this article you can get acquainted with: operations carried out during the maintenance of the vibration meter; norms of time for performing operations; vibration meter maintenance strategy. Operations Discharge Execution time (hour) Maintenance strategy Visual inspection: check for mechanical damage, removal of contaminants. 5 0.05 TO3 Checking the reliability of electrical connections and grounding. 5 0.12 TO3 Checking the transducer in the “control” mode, adjustment.…

Category: Tags: ,

In this article you can get acquainted with: the operations carried out during the maintenance of the level sensor-switch; norms of time for performing operations; level sensor maintenance strategy. Operations Discharge Execution time (hour) Maintenance strategy External inspection in accordance with the requirements for explosion-proof equipment, removal of contamination. 6 0.11 TO3 Cleaning of electrodes (contacts), checking operation. 6 0.27 TO3

Category: Tags: ,

In this article you can get acquainted with: the operations carried out during the maintenance of the filling level limiter; norms of time for performing operations; filling level limiter maintenance strategy. Operations Discharge Execution time (hour) Maintenance strategy Visual inspection: check for mechanical damage, removal of contaminants. 4 0.06 TO3 Checking the tightness of the sensor connections. 4 0.13 TO3 Leak test shut-off valve

Category: Tags: ,

In this article you can get acquainted with: the operations carried out during the maintenance of the displacer pneumatic level gauge; norms of time for performing operations; maintenance strategy of the displacer pneumatic level gauge. Operations Discharge Execution time (hours) Maintenance strategy Supply air pressure check, adjustment 4 0.06 TO3 Visual inspection: check for mechanical damage, remove dirt. 4 0.06 TO3 Cleaning the throttle, nozzles ...

Modern industrial enterprises in their production process can not do without the use of instrumentation and automation. Automation has been introduced both at heavy engineering enterprises and in food production. In everyday life, installations are used to account for the consumption of water resources, electrical and thermal energy. The main purpose of the devices is to accurately determine the physical quantity. timely repairs and maintenance of instrumentation guarantee the accuracy of the devices.

Characteristics of measuring instruments

There are high requirements for quality characteristics and accuracy of measurements made to control and measuring devices. They form several groups:

  • Devices for measuring pressure;
  • Devices for measuring the volume of bulk and liquid substances;
  • Devices for determining switching costs;
  • Protection devices.

It is possible to determine the indications of a physical quantity on a scale and an installation indicator, they are classified according to the location of the scale. According to the location of the scale indicators, the devices are defined by two types: one-sided and two-sided. One-sided devices include devices in which the scale with the beginning of the readings is located on the left side and is limited to one direction. Dual-sided settings are devices where the zero scale position is located in the center and the values ​​​​are determined on the right and left sides of the center.

Types of repair work

Exclude emergency in production, you can use the recommendations of the provisions on maintenance and repair of instrumentation. The maintenance and repair system determines the types of repairs and the list of repairs, frequency of maintenance of instrumentation and instrumentation, consumption rates of materials and spare parts. The system of scheduled preventive maintenance includes checking of measuring instruments, major and current repairs, as well as maintenance of instrumentation and instrumentation.

The equipment of the enterprise involved in the production process is stopped for scheduled repairs, but there are also emergency stops. At the time of an emergency stop, repair operations are performed that cannot be performed with the equipment running. Planned stops are carried out on the basis of a schedule, which is formed taking into account frequency of instrumentation maintenance.

The maintenance of the equipment in working order ensures the monthly - TO-1, quarterly - TO-2, annual - TO-3. During the period of scheduled shutdowns, the dismantling of measuring structures, as well as automation equipment, pipe and cable wiring, is carried out. The duration of the repair period is determined on the basis of norms of time for maintenance of instrumentation.

List of requirements for performers of work

Ensure the performance of instrumentation and automation, specially trained workers. Given the complexity of automation systems, engineers and specialists with specialized education are engaged in launching the production of installations. depends on the performance of the equipment production activity enterprises.

Maintenance of instrumentation are carried out by employees of the enterprise or specialists of a contracting organization who have documents certifying the right to carry out repair work of measuring instruments. The contractor must have:

  • trained personnel;
  • repair base;
  • Normative and technical documentation.

In fact, the mastered volumes of repair work are monthly drawn up bilaterally by an act of delivery of work performed.

The main goal of performing preventive repair work is to increase the productive efficiency of the enterprise, to ensure the safety of the production process. Also carry out control of production technology, ensure labor safety and environmental safety, equipment performance. The stability of the production process of the enterprise depends on the implementation of measures aimed at introducing new technology and replacement of obsolete equipment. accident-free manufacturing process provide scheduled preventive maintenance. Their planning is carried out taking into account the frequency maintenance of instrumentation and instrumentation.

Verification of instrumentation and automation is carried out to determine the conformity of characteristics state standards and technical conditions. Production metrological supervision regulated by GOST. Depending on the purpose of the tested measuring instrument, verification can be carried out public service or a departmental metrological organization.

STANDARDS OF TIME FOR THE ADJUSTMENT OF INSTRUMENTATION AND A DEVICES, TECHNOLOGICAL PROTECTION AND ALARMS AT THERMAL POWER PLANTS

A COMMON PART

1. These Standards of time for setting up instrumentation and A devices, technological protection and signaling at thermal power plants are recommended for use at enterprises of the Ministry of Energy of the Russian Federation and are intended for issuing standardized tasks to time workers and job orders to piece workers.

2. For the development of time standards used;

Photochronometric observations;

Technical calculations;

Technical descriptions and operating instructions for devices, drawings developed by manufacturers;

Guidelines for the regulation of labor in the energy sector (Decree of the Ministry of Energy and Electrification of the USSR dated 10.05.76 No. NS-6594);

The results of the analysis of the organization of labor and measures to improve it at thermal power plants of the USSR Ministry of Energy.

3. Time limits are calculated by the formula:

where: T op - operational time for the operation, man-hour;

a about - time for maintenance of the workplace, percentageoperational time;

a pz - time for preparatory and final work, percentage of operational time;

a exc - time for rest and personal needs, percentage of operational time;

a Fri - time for technological breaks, percentage of operational time;

4. The time standards are set for adjustment work performed by at least two performers in the conditions of existing workshops, and are indicated inman-hours (person-hour).

5. The norms take into account the time for:

Preparatory and final work - 5.7% of operational time;

Maintenance of the workplace - 3.0% of the operational time;

- rest and personal needs - 10% of operational time;

Technological breaks - 3.0% of operational time;

Transitions of the performer within the working area at a distance of up to 50 m and when performing work at a height of up to 1.5 m.

The time spent on preparatory and final work and maintenance of the workplace includes time for:

Obtaining a job assignment, tools, fixtures, technical, documentation;

Briefing on the order of work;

Delivery of fixtures, tools, technical documentation;

Workplace maintenance.

6. The norms do not take into account the time for:

Dressing up;

Work permit;

Closing the outfit;

Delivery of the outfit;

Transitions of workers over a distance of more than 50 m.

7. When ringing cable lines with the number of cores above 10 time norms, apply with the following coefficients: 1.30 for more than 10 to 19 cores; 2.30 - over 19 to 37 cores; 3.00 - over 37 cores.

8. The scope of work for the adjustment of instrumentation and control devices, technological protection and signaling includes:

Acquaintance with technical documentation, drawings;

Inspection of the scheme;

Checking the reliability of contacts;

Continuity of individual circuits;

Checking electrical strength and determination of insulation resistance;

Checking individual elements and replacing faulty ones;

Laboratory testing of regulators;

Static adjustment of regulators;

Setting parameters for dynamic adjustment of regulators;

Enabling regulators to work and adjusting settings;

Testing of individual circuits and complex testing of the circuit;

Adjustment of the mechanical part of regulating, managing and otherexecutive bodies;

Adjustment of the measuring control system of the IMS;

Paperwork.

9. The name of the profession "Electric fitter for the repair of thermal mechanical control devices and automation of thermal processes" (hereinafter for brevity - electric fitter) and the categories of workers are indicated in accordance with the "Unified Tariff and Qualification Reference Book of Works and Professions of Workers". Issue. 9, Moscow, 1985 Qualification guide positions of managers, specialists and employees". Moscow, Economics, 1989.

10. The performance of work by workers whose qualification categories do not correspond to the categories of workers given in these Standards cannot serve as a basis for changing the norms of time for these works.

11. If in the Norms the values ​​of length, time, etc. are given with the word "until", it should be understood as "inclusive".

12. For work not provided for by these Standards, local technically justified time standards are established.

13. Prior to the introduction of these Time Standards, it is necessary to carry out organizational and technical conditions in workshops, production sites and workplaces (organization of labor, equipment, etc.) in accordance with these Standards and carry out production instruction for workers.

14. When introducing at enterprises more advanced than provided for by these Regulations, the organization of production, labor, technological works, equipment, machines, equipment or standard projects for organizing workplaces, etc., providing a higher level of labor productivity for workers, are developed by the method of technicallabor rationing and local time standards are put into effect in the prescribed manner.

15. With the introduction of these Time Standards, all previously existing standards for the relevant work, except for more progressive ones, are canceled.

Characteristics of the equipment used

The full document can be downloaded from the link at the top of the page.

One of the current compendia that contains maintenance standards and allows you to determine the number of personnel, as well as the cost of maintenance of security systems.
Here are excerpts from this document, which is called:

"Labor standards for auxiliary work in housing and communal services"

Status:

current

Date of entry into force:

Developed in:

CJSC "Center for Municipal Economics and Law" 101000, Moscow, Mospochtamt, PO Box 348
JSC "Center of Municipal Economics" 101000, Moscow, st. Myasnitskaya, 13, building 3

Approved in:

JSC "Research Center of Municipal Economy" (01.01.2006)

JSC "Center of Municipal Economics" No. 2006

Scope and conditions of application:

This collection contains labor standards for auxiliary work performed in the provision (production) of housing and communal services (goods) by enterprises and organizations of any organizational and legal forms.
The recommendations are intended to determine the labor intensity of work and the standard number of employees of housing and communal services organizations, on the basis of which labor costs are calculated in economically justified tariffs for housing and communal services.

2.6. Maintenance and current repair of radio and television equipment and low-current equipment

2.6.1. Installation and repair of individual receiving antennas *

Approximate list of works. Determining and preparing the antenna installation site, lifting the antenna to the roof of the building, assembling the antenna, connecting the drop cable, connecting the antenna to the lightning protection device, laying the cable along the roof, entering the cable into the room, soldering the plug, turning on the TV and orienting the antenna to the best image, quality verification work.

Checking the absence of voltage on the mast and guys. Loosening and removing the guy wires, lowering and repairing the antenna, checking the reliability of connecting the drop cable and fastening the elements, installing the antenna with guy wires, turning on the TV and orienting the antenna to the best image. Checking the quality of the TV.

Cast: radio receiver of receiving television antennas.

Table 2.6.1.

Types of antennas

Norms of time per antenna, hour

norms

installation

repair

Receiving television antenna of the meter wave range, single-channel, one-five-element

2,46

1,78

Receiving television antenna of the meter range of waves, two-channel, four-six-element

2,46

1,93

Receiving television antenna of the meter wave range, multi-channel, one-two element

2,50

1,88

Receiving television antenna of the meter range of waves, multi-channel, seven-element

2,31

1,82

Receiving television antenna of the decimeter wave range, multi-channel, multi-element

2,57

1,70

Notes:
1. The norms of time for the installation of antennas do not take into account the construction of lightning protection devices.
2. Antenna repair times do not include drop cable replacement.
Individual receiving antennas include: antennas of the meter and decimeter wave range, single-channel and multi-channel.

2.6.2. TV equipment

2.6.2.1. Replacing the cable to reduce the receiving television antenna

Approximate list of works. Checking the absence of voltage on the mast and guys. Loosening or removing guy wires, lowering the antenna. Replacing the drop cable with a new one, installing the antenna, turning on the TV and orienting the antenna for the best picture. Checking the operation of the TV.
The composition of the performers: radioman of receiving television antennas.
The norm of time for 1 antenna is 1.65 hours.

2.6.2.2. Laying a subscriber television cable with connection to a junction box and a TV

Approximate list of works. Marking and preparing the route for cable laying, laying and fastening the cable, connecting the cable to the junction box, terminating the plug, measuring the mains voltage. Connecting the TV to the network and checking its operation.
Cast: radio receiver of receiving television antennas.
The norm of time for 10 m of cable is 1.22 hours.

2.6.2.3. Connecting a subscriber cable to a junction box (without laying a cable) and minor repairs to a subscriber branch

Approximate list of works.Checking the absence of voltage on the mast and guys. Checking the correct laying of the subscriber cable, connecting the cable to the junction box, sealing the plug. Disconnecting the subscriber cable with or without removing the cable, unsoldering the plug, connecting the cable from several pieces and other minor repairs to the subscriber branch. Checking the operation of the TV.

The composition of the performers: radioman of receiving television antennas.
The time limit for 1 connection is 0.91 hours.

Note:
Time limits of paragraphs 2.1.7.1.-2.1.7.2. installed taking into account the installation and repair of outdoor receiving antennas with a mast height of up to 3 meters.
In cases of installation and repair of these types of antennas with a mast height of more than 3 to 6 meters or 2-story (two-tier) antennas, 1 hour is added to the time standards of these sections.

2.6.3. Fire extinguishing installations, security, fire and fire alarm systems

An indicative list of professions: adjuster of instrumentation and automation, locksmith for instrumentation and automation, electrician for the repair of electrical equipment, electrician of fire and security alarms.

Table 2.6.3.

Name of equipment

Norm No.

Maximum action automatic thermal switch

0,56

Fire-fighting signal-starting block

2,39

0,45

Non-contact electromagnetic sensor

0,17

0,05

block-contact sensor

0,75

Sensor inertial magnetic contact

0,19

0,19

Magnetic contact sensor

0,36

Infrared sensor

0,67

0,68

Shock contact sensor

0,30

Electrocontact sensor

1,10

howler call

0,23

Automatic security detector

1,49

0,65

Automatic fire and security detector

6,84

0,96

Radioisotope smoke detector

1,20

0,79

Photoelectric smoke detector

0,39

0,16

Combined detector

1,44

Optoelectronic security and fire detector

4,80

0,79

Detector security and fire surface ultrasonic

5,43

Burglar alarm detector

5,80

4,49

fire detector

0,17

0,05

Fire detector maximum-differential bimetallic automatic

0,37

Thermal magnetic fire detector

0,29

Manual fire detector

0,20

0,97

light detector

1,62

Fire alarm detector

0,0087

detector

1,90

0,58

Automatic thermal detector

4,56

4,25

Thermal detector with fusible lock

0,29

intrinsically safe device

3,87

1,13

concentrator

8,20

0,97

Small capacity hub

1,17

0,08

Concentrator reception and control security and fire

6,27

1,59

Concentrator signal-starting firefighter

3,20

0,22

Linear signaling unit

0,21

Line block device

14,4

0,38

microswitch

Intermediate executive body

5,95

burglar alarm device

0,44

0,71

Control panel device

6,87

0,51

Reception and control device for security and fire

0,96

Signaling device:

— for 1 linear set

— for 9 sets

4,52

Signaling device

0,61

Intrusion alarm device

3,19

Piezoelectric signaling device

0,17

Radio wave signaling device

0,92

Single-beam piezoelectric signaling device

Control panel

6,99

1,15

Fire alarm panel

2,45

1,44

signaling device

2,00

0,59

Siren alarm

0,31

station apparatus

4,28

1,37

fire alarm station

18,06

0,63

Thermodetector in explosion-proof design

4,95

Installation radioisotope security and fire

20,47

1,43

Smoke alarm installation

8,67

1,64

Installation signaling complex fire

56,00

1,10

Device for monitoring the destruction of glazed structures

2,00

2,07

Object receiving and control device

5,14

Security alarm device

5,66

0,77

Intermediate receiving and control device

1,04

0,26

signaling device

0,56

0,21

Photoelectric device

3,00

1,66

Alarm loop single-pair and multi-pair (5 m)

0,02

0,72

Note :
1. The staffing standards provide for the performance of maintenance work for a concentrator with one unit. When using an additional five-beam block, the standard increases by 60%.
2. The staffing standard provides for the performance of maintenance work for the station with one 10-beam unit. When using an additional block, the standard increases by 40%.
3. The staffing standard provides for the performance of maintenance work for the unit with one BKL-1 unit. When using an additional block BKL-1, the standard increases by 70%.

2.6.4. Means of chemical, automatic gas, water and foam fire extinguishing

Approximate list of works (maintenance).

External inspection, control of the technical condition (operable-inoperable, serviceable-faulty) using the sense organs and, if necessary, control means, the nomenclature of which is established by the relevant documentation, i.e. determination of the technical condition of installations and individual technical means according to external signs.

Performance check: determination of the technical condition by monitoring the implementation by technical means and the installation as a whole of part or all of their inherent functions determined by the purpose.

Cleaning the external surfaces of technical equipment, checking the technical condition of their internal installation (internal surfaces), cleaning, grinding, lubricating, soldering, replacing or restoring elements of technical equipment that have expired or become unusable, adjusting, setting up devices, testing and checking them.

Approximate list of works (current repairs). Cleaning of external surfaces of technical facilities, partial disassembly, replacement or repair of equipment of individual units, parts, line-cable structures, etc. carrying out measurements and testing of equipment, if these data do not correspond to passport data, measures are taken to eliminate defects. Cleaning, lapping, lubricating, soldering, adjusting, setting instruments, testing and checking them.

Approximate list of professions: adjuster of instrumentation and automation, mechanic-repairman, electrician for the repair of electrical equipment.

Table 2.6.4.

Name of equipment

Standards for the number of workers involved in the maintenance of equipment, pers. for 100 units equipment

Norms of time for the current repair of equipment, man / hour per unit. equipment

Norm No.

Battery six-balloon (8-balloon)

0,13

Flanged cast-iron diaphragm shut-off valves with electric drive

0,75

Flanged cast iron shut-off valves

0,25

Flanged cast iron shut-off valves with electromagnetic drive and electromagnetic latch

0,62

Flanged cast iron and steel shut-off valves with electric drive

0,54

Generator

0,24

High expansion foam generator

0,14

0,04

Two-jet generator

0,08

0,04

Involute generator

0,02

Rising stem gate valves, flanged steel

0,93

1,51

Gate valves with rising stem, flanged steel with electric actuator in explosion-proof design

5,31

1,51

Flanged cast iron parallel valve with rising stem

0,92

1,51

Gate valves with electric drive

1,77

1,51

Flanged cast iron non-return valve with mesh

1,96

Incentive cable valve

1,54

1,49

Rotary single disc cast iron flanged valve

0,39

1,99

Manual valve

0,20

Trial-start stuffing box brass valve

0,15

Compressor

10,88

9,08

Connecting lines (100 m)

Pump

4,89

Water sprinkler and deluge sprinkler

0,29

Sprinkler foam sprinkler, involute

0,23

Air distributor

1,23

0,15

Battery section

4,00

0,20

Universal pressure indicator

1,39

0,20

Liquid flow switch

6,00

0,63

Dosing signaling device

charging station

3,33

0,42

Automatic gas fire extinguishing installation

2,66

0,13

Freon fire extinguishing installation

4,55

3,84

Signaling and control board

7,36

Power cabinet for electric valves

16,95

Carbon dioxide fire extinguishing cabinet with hose and socket

1,98

Control cabinet

18,93

Gate valve motor control cabinet

20,28

Electromagnetic pressure gauge

0,33

2.6.5. Fire automatics

External inspection, control of the technical condition (operable-inoperable, serviceable-faulty) using the sense organs and, if necessary, control means, the nomenclature of which is established by the relevant documentation, i.e. determination of the technical condition of installations and individual technical means according to external signs.

Performance check: determination of the technical condition by monitoring the implementation by technical means and the installation as a whole of part or all of their inherent functions determined by the purpose.

Cleaning the external surfaces of technical equipment, checking the technical condition of their internal installation (internal surfaces), cleaning, grinding; lubrication, soldering, replacement or restoration of elements of technical means that have expired or become unusable, adjustment, adjustment of devices, testing and checking them.

Cleaning of external surfaces of technical facilities, partial disassembly, replacement or repair of equipment of individual units, parts, line-cable structures, etc. carrying out measurements and testing of equipment, if these data do not correspond to passport data, measures are taken to eliminate defects. Cleaning, lapping, lubricating, soldering, adjusting, setting up instruments, testing and checking them.

mechanic-repairman, electrician for the repair of electrical equipment.

Table 2.6.5.

Name of equipment

Standards for the number of workers involved in the maintenance of equipment, pers. for 100 units equipment

Norms of time for the current repair of equipment, man / hour per unit. equipment

Norm No.

Tank for filling pumps

5,00

0,07

Automatic two-balloon battery with electric start

6,20

0,27

Two-balloon battery

2,50

0,15

Battery with automatic and pneumatic start

6,60

Horizontal tank (hydro-pneumatic tank)

7,20

2,39

Foaming storage tank

4,40

1,58

Incentive-starting section with control valve

5,70

0,98

Water sprinkler control unit with valves

4,48

1,66

Air sprinkler control unit with valves

5,12

1,66

17,00

1,66

Air-water sprinkler control unit with valves

10,00

1,66

Control unit for deluge plant with hydraulic start with valve

9,37

1,66

Control unit for deluge plant with pneumatic start with valve

8,50

Control unit for deluge (sprinkler) installation with valve

- sprinkler installation of an air-water fire extinguishing system or deluge installation with pneumatic start-up, taking into account the number of vehicles included in the control unit

6,60

- control unit of a deluge plant with hydraulic start, taking into account the number of vehicles included in the control unit

4,80

- control unit of the sprinkler installation of the water system, taking into account the number of vehicles included in the control unit

4,70

Sprinkler control unit with valve

2,70

3,35

Distribution device (taking into account the number of vehicles included in the device)

3,30

0,58

Note: To determine the standard number for the performance of maintenance and repair of installations that are carried out at a height of more than 5 m from the floor, the following coefficients are applied, respectively:

from 5 to 8 m - 1.05

from 8 to 15 m - 1.10

from 15 to 30 m - 1.25

2.6.6. Communication equipment

Approximate list of works (maintenance).

External inspection, control over the technical condition of communication equipment, elimination of detected defects, electrical changes in certain sections of station, line, feeder and other communication facilities.

Approximate list of works (current repairs).External inspection, partial disassembly, replacement, repair of parts and assemblies, line-cable structures, measurements and testing of communication equipment, electrical measurements in certain sections of station, line, feeder and other communication structures.

Approximate list of professions:electrician of sewer communication facilities, electrician of linear telephone and radio installations, electrician of station radio equipment, electrician of station telephone equipment, electrician of station radio equipment.

Table 2.6.6.

Name of equipment

Meter

Standards for the number of workers, pers.

Norm No.

Total

including:

those. service

Maintenance

Cable lines:

Communication lines with cable type:

MKS 1?4 and all low-frequency cables

10 km cable

0,21

0,19

0,02

ISS 4?4

-«-

0,23

0,20

0,02

MKS 7?4, VKAP

-«-

0,24

0,22

0,03

Tie trunk cables:

Sealing up to 30 channels

10 km cable

0,21

0,19

0,02

Sealing over 30 channels

-«-

0,23

0,20

0,02

Unsealed cables on tie trunks

-«-

0,06

0,05

0,06

Subscriber lines and radio lines

-«-

0,05

0,04

0,05

Radio cables

-«-

0,021

0,18

0,023

GTS cable lines:

With an average capacity of up to 50 pairs of cores

10 km couple lived

0,005

0,004

0,0005

With an average capacity of more than 50 pairs of cores

-«-

0,003

0,002

0,0003

Sewer devices

canal-km

0,025

0,022

0,003

Broadcast points

100 radio points

0,016

0,014

0,002

Loudspeaker communication equipment

100 instruments

1,16

1,03

0,13

Direct dial telephone

100 devices

0,06

0,05

0,005

PBX telephone set

-«-

0,012

Telephone set

-«-

1,44

1,28

0,16

telephone set-top box

100 consoles

1,21

1,08

0,13

ATS of a decade-step system with a capacity of 100 or more numbers

100 monitored numbers

0,18

0,02

ATS coordinate system

-«-

0,09

0,08

0,01

electric clock

100 electric hours

1,15

0,92

0,23

Note:
1. With an increase in the average number of channels, the standard is reduced at the rate of: for every 0.5 channels by 10%.
2. For 2-3 program networks, the standard is increased by 10%.

An example of calculating the number of workers involved in the maintenance and current repair of radio and television equipment and low-current equipment

Number of paragraph according to the collection

Scope of work

Scope of work

Norm of time, man-hour

Annual standard labor intensity, man-hour

2.6.2.1.

Installation of a receiving television antenna of the decimeter wave range

157 antennas

2,57

403,49

2.6.2.2.

Laying a subscriber television cable

1,22

383,08

2.6.3.

Current repair of a photoelectric smoke detector

0,16

9,12

2.6.4.

Current repair of automatic gas fire extinguishing installation

0,13

9,88

TOTAL

805,57

The list number of workers engaged in the maintenance and current repair of radio and television equipment and low-current equipment is:

(805,57/1992) ?1.12 \u003d 0.45? 0.5 people

where: 1992 - annual fund of working time;

1,12 — coefficient of planned absenteeism.

2.8. Other support work

2.8.3. Standards for the number of watchmen

Approximate list of works.Duty at entrance doors protected object, checking the integrity of the protected object (locks and other locking devices), the presence of seals, the serviceability of alarm devices, telephones, lighting, the availability of fire fighting equipment.

To determine the number of guards, it is necessary to establish:
the necessary and rational number of posts in the building, which depends on the number of buildings, isolated entrances, etc.;
the number of shifts for each post.
The standard for the number of watchmen per shift for 1 post is 1 person.

Download the full text of the document— Please or to access this content

A complete list of the main collections for maintenance of security systems includes the following documents:

- MTSN 81-98 and TSN-2001.14-15 Collection 15. Technical operation communications, video surveillance systems, traffic control, security and fire alarms
– RTM 25 488 82 Ministry of Instrumentation of the USSR. Automatic fire extinguishing installations and installations of fire and security, and fire alarm systems. Standards for the number of personnel involved in maintenance and current repairs.
— Price list No. 2661 00192.“System of maintenance and repair of technical means and systems of fire extinguishing, smoke removal, security, fire and security fire alarms. Wholesale prices for maintenance and repair”, developed and implemented by MGO “Protection” (Tver). The price list was issued in 1991 prices and entered into force on April 1, 1992;
— GESNmt 81-03-42-2001 Collection No. 42 Maintenance, repair and modernization of equipment of complex integrated) security systems.
— VESNMT CBR with rev. from 6.07. 2006 Maintenance of engineering and technical means of protection (a copy of GESNmt-42 with a different name).
— RD 08.00-60.30.00-KTN-016-1-05“Procedure for carrying out, technological maps, unit norms and prices for maintenance of engineering and technical means of protection of facilities of enterprises that are part of the TRANSNEFT group of companies.
- Instruction of the Ministry of Internal Affairs of the Russian Federation on the organization of the operation of technical security equipment at facilities protected by private security
— OESN-81-26-09-2003 Systems of technological control, regulation, protection and control. Means of signaling, computer technology, telemechanics and communications.

All of these documents can be obtained from information base for the maintenance and repair of security systems, complete with a program for automatically calculating the estimated cost of MRO.

In 2009 passed state expertise and a new collection for maintenance is being prepared for printing, which contains technological maps, time standards and examples of documentation for the maintenance and repair of security systems. We will provide detailed information on this collection in the coming months, as soon as the collection is published in print. Follow the publications or to quickly receive information automatically from our website.